It said the high-specification units will each be delayed by six months each, while the period between deliveries of each rig has been extended.

As a consequence the first of the Super B Bigfoot-class jack-ups will now be delivered in the third quarter of 2016 versus the first quarter.

Transocean had originally planned to take delivery of the rigs from the Singapore yard at four-month intervals.

“The